Although not in the Parish, residents may well be affected by the proposed closure of the A225 from January to March next year. With the agreement of Borough Councillor George Holt the following Facebook message has been posted for your information
IMPORTANT UPDATE: SGN GAS MAIN REPLACEMENT WORKS - JANUARY TO MARCH 2027
Many residents will have received a letter from SGN advising of planned gas main replacement works scheduled to commence in January 2027 and finish in March. I've now got a more comprehensive update, and give thanks to
Alan White - Councillor for Horton Kirby, South Darenth and Farningham who's been pushing on KCC's and SGN's door to get more information on this.
The A225 will be closed between Station Road and Franks Lane for the duration of this period. The official diversion is a 38-minute round trip through Darenth, Longfield, Meopham, Culverstone Green, through the A227, and then the A20 (link in the comments).
We're still trying to get more information from KCC and SGN, but here's what we know so far.
Why are SGN/KCC closing the roads?
Many of you will remember the gas maintenance works carried out along the A225 earlier this year by SGN and its contractors, WCB. At that time, temporary traffic lights were used to minimise disruption. However, four sections remain where the gas mains run beneath the centre of the carriageway. Unfortunately, they will need to fully close the A225 to allow this final stage of essential maintenance to be completed safely.
Why didn't they complete this work during their previous closure?
This was due to a fault on SGN's side, as when the work was originally completed, their maps did not correctly show where the pipes were. Meaning they now need to return to complete the outstanding work.
When will the works take place?
The road closure is scheduled to commence on Monday, 4 January 2027, with the project expected to take approximately 12 weeks, concluding towards the end of March 2027.
Residents and businesses along the A225 will retain access to their properties, and businesses will remain open.
During previous SGN roadworks, a traffic modelling exercise indicated that approximately 70% of displaced traffic would use Horton Kirby as a cut-through when the A225 is affected.
Due to concerns over safety, KCC/SGN considered it essential to prevent Horton Kirby from becoming a diversionary route for through traffic. As a result, Eglantine Lane will be closed between the crossroads with Lombard Street and the entrance to Eglantine Villa Care Home and the Storage Yard. Residents of Saxon Place and those accessing the care home will be able to exit Eglantine Lane via the A20.
There are also several other measures being pursued by Councillors to help manage the disruption:
1) SATELLITE NAVIGATION: We have asked SGN to notify the relevant satellite navigation providers well in advance so that the closures and diversion routes are reflected in their systems.
2) NATIONAL HIGHWAYS: We are seeking additional signage along the A20 to discourage drivers from using unsuitable alternative routes when congestion or incidents affect the M25, Dartford Crossing or surrounding junctions.